NERSA registration for grid-connected generation below 100 MW: indicative 8–10 weeks from complete submission. Incomplete applications reset the clock.
Parallel workstreams: environmental authorisation (where triggered), grid connection study, and PPA negotiation should start during origination — not after registration.
Grid access remains the binding constraint on most projects. Early engagement with NTCSA or the relevant distributor is critical path.